Works consisted of demolition and alteration works to the existing structure and the erection and completion of a warehouse comprising foundations, steel frame, insitu concrete floors, cavity wall construction, solid wall construction, cladding to walls and roof.
The works were completed within a live environment with connections to existing buildings. Works were completed 5 weeks ahead of schedule.