Works progressing well at the National Indoor Arena

Our HBJV Team has moved on site at the National Indoor Arena with works progressing well over the last six weeks.

niaStory

The project will comprise of:

  • National Indoor Athletics Training Centre – including 200m track; 60m sprint track; 110m sprint track; throw, jump and pole-vault areas; permanent seating for 400 spectators which can be increased to 1,900 for key events
  • National Gymnastics Training Centre – catering for all gymnastics

Disciplines

  • National Indoor Training Centre – a multi-sport facility catering for over 20 sports in a variety of configurations; capable of being sub-divided into 3 separate areas; seating for 1,500 spectators
  • Covered synthetic pitches with ancillary changing, strength & conditioning facilities etc.

Works completed to date include site establishment, reduced dig and soil stabilization, established traffic management of the existing campus roads network to facilitate the new project works and one kilometer of boundary fencing has been erected.

Upcoming works include the excavation and pouring of concrete foundations, erection of the structural steel frame in mid July, and commencement of below ground drainage and utility works.

We are also hosting a Meet the Buyer event on the 4th June to promote local supply chain opportunities.  For more information about the event please click on this link www.heronbros.com/interested-in-working-on-the-national-indoor-arena-project/

It is intended to phase the construction of the Arena, with completion of the Athletics, Gymnastics and multi-sport facilities scheduled for November 2016.

For more information on the National Indoor Arena contact Shauna Young onshauna.young@heronbros.com .