Gallahers Gallahers Gallahers

The 210,000 sq. ft. industrial unit was designed and built on a fast track basis to achieve the required completion deadline.

The unit was built on a pre-war brown field site requiring considerable on-site survey, demolition and imaginative design proposals at the abutment with existing structures. The total design and build period was achieved within 22 weeks to coincide with 1 year planned tenant relocation.

This required extensive pre and post contract co-ordination and programming. The co-ordination was enhanced via the use of an internet-based project management system providing all members of the design and construction team immediate access to all the latest design information.